Project Summary
Project includes removal and replacement of the multi-purpose athletic field, sports lighting system, both basketball courts, and playground equipment; new electronic scoreboard; lighting retrofits for the basketball courts, tennis courts, and park restrooms; resurfacing and restriping of the tennis courts; new pickleball courts with fencing and lighting retrofits; new park lighting, walking paths, ADA improvements, and bicycle connections; repaving and restriping of the parking lot on the west side of the park; landscaping and drainage improvements; public safety cameras; park signage; trash receptacles and recycling containers; picnic tables, benches and shade structures.
Timeline
See the project timeline below for El Toyon Park Improvements.
Funding
See the funding sources below for El Toyon Park Improvements.
Project Updates
DATE:
June 12, 2026
UPDATE:
Past 2 Weeks
-
Completed construction on the ADA ramp and crossing on S . U Ave & 1st
-
Completed construction of the agility course
-
Completed the installation of bleachers
2 Week Look Ahead
-
Complete the stucco on the monument signs
-
Complete the asphalt paving at the West parking lot
Locations Impacted
- No streets will be impacted at this time
- The West side of El Toyon Park and the adjacent parking lot will be closed for construction
- The East side of El Toyon Park will remain open, with the areas of construction designated & cautioned off as needed
Project Team
Contractor:
Company Name
Contact Name
Address
City, State, Zip
Phone
Email
Project Manager:
Project Professionals Corporation
Josh Johnson, PE
4700 Spring Street, Suite 100
La Mesa, CA 91942
858.634.8180
Administrator:
City of National City
Steve Manganiello, TE
1243 National City Blvd
National City, CA 91950
619.336.4380